Meeting Minutes — 2026-01-08
Date: 2026-01-08
Time: 13:30–14:00 CET
Location: Google Meet
Attendees:
- Viktor Semenov
- Marco Potenza
- Edward Yusko
- Yurii Chabanov
- Mykola Surygin
- Volodymyr Shevtsov
- Pavlo Kalinkin
Agenda
- Development progress on Reseller functionality
- Timestamp format in raw CSV export
- Client presentation status of the MyMaxwell portal
- Remaining work to eliminate last bugs before release
- Documentation portal for requirements alignment
- Azure Application Service Plan migration to Linux to reduce infrastructure costs
Notes & Discussion
1. Development progress on Reseller functionality
There is still a significant amount of work to be done. Progress is highly dependent on timely management input.
2. Timestamp format in raw CSV export
The yyyy-mm-dd hh:mm:ss format now works universally across all locales in Microsoft Excel. This change has not yet been deployed to production.
3. Client presentation of the MyMaxwell portal
Edward: A newsletter will be sent on January 14th to 75 distributors, stating that some already have access to the MyMaxwell portal. There are many requests coming through sales representatives for access.
As a result, the team should be ready to support 2–3 HTMS-friendly distributors after January 14th and address their feedback and complaints. These distributors should be selected together with Tom and Ben.
4. Remaining work to eliminate last bugs
Viktor: There is nothing preventing a release in principle. Final fixes to client documents are still pending and are expected to be released next week; these can then be used.
Efficiency calculations still have minor issues, but these are purely mathematical nuances and not considered critical. The raw CSV export date format issue has been fixed.
5. Documentation portal for requirements alignment
Edward was invited to review the portal documentation available at
https://docs.mymaxwell.net
6. Azure Application Service Plan migration to Linux
Azure Windows-based service plans are approximately four times more expensive than Linux-based plans. The application runs well in a Linux environment; this has been tested in development and is planned for release to production next week.
Decisions Made
- No formal decisions were made; the call served as a progress sync.
Action Items
| Action Item | Owner | Due Date | Status |
|---|---|---|---|
| Provide IP address(es) for documentation portal access | Edward | 2026-01-09 | Pending |
| Switch production service plan to Linux | DevOps | 2026-01-13 | Pending |
| Select 2–3 pilot distributors with Tom and Ben | Edward / Mgmt | 2026-01-14 | Pending |
| Deploy fixed CSV timestamp format to production | Dev Team | 2026-01-13 | Pending |